Energy Generation and Transmission Siting (CPCN) Cases

(Certificates of Public Convenience and Necessity)

2024

  • Case No. 9726 – Chaberton Solar Sugarloaf I, LLC
    4.0 MW solar facility (Montgomery County)
  • Case No. 9725 – Chaberton Solar Pine Rocks, LLC
    3.0 MW solar facility (Carroll County)
  • Case No. 9723 – Crockett Solar I, LLC
    61.2 MW solar facility (Talbot County)

2023

  • Case No. 9717 – Chaberton Solar Wild Turkey, LLC
    5.0 MW solar facility (Frederick County)
  • Case No. 9716 – Chaberton Solar Bonneville, LLC
    5.0 MW solar facility (Harford County)
    Virtual public hearing: Wednesday, April 10, 2024 at 7 p.m.
  • Case No. 9714 – Chaberton Solar Snow, LLC
    4.0 MW solar facility (Worcester County)
    Virtual public hearing: Tuesday, April 30, 2024 at 7 p.m.
  • Case No. 9713Baltimore Gas and Electric Company
    Fitzell Third and Fourth Circuits Reconfiguration Project (Baltimore County)
  • Case No. 9710Porter Mill, LLC
    45.8 MW solar facility (Wicomico County)
  • Case No. 9699 Potomac Electric Power Company
    Oak Grove-Talbert 230 kV overhead tower line rebuild (Prince George’s County)
    Order No. 91060: March 14, 2024
  • Case No. 9698Delmarva Power & Light Company
    Vienna Substation-Maryland/Delaware State Line 138 kV transmission line rebuild (Dorchester County, MD to Sussex County, DE)
    Order No. 90950: December 19, 2023
  • Case No. 9694 Kumquat & Citron Cleantech, LLC
    7.2 MW solar facility (Wicomico County)

2022

  • Case No. 9685 Community Power Group, LLC
    5.0 MW solar facility (Anne Arundel County)
  • Case No. 9684 Rosehip Cleantech, LLC
    4.0 MW solar facility (Somerset County)
  • Case No. 9682 Temo Renewables, LLC
    9.9 MW Walston I solar facility (Wicomico County)
    Order No. 90756: August 14, 2023
  • Case No. 9677 Constellation Power Source Generation, LLC
    Modifications to the Perryman Generating Station (Harford County)
    Order No. 90313: August 19, 2022
  • Case No. 9675 Waypost Solar Project, LLC
    92.0 MW solar facility (Caroline County)
    Order No. 90446: December 16, 2022
  • Case No. 9437–CPV Maryland, LLC
    Modifications to the St. Charles Generating Station (Charles County)
    Order No. 90312: August 17, 2022

2021

  • Case No. 9669–Potomac Edison Company
    Doubs-Goose Creek 500kV Transmission Line Rebuild (Frederick County to Montgomery County)
    Order No. 90684: June 27, 2023
  • Case No. 9663–CPV Backbone Solar, LLC
    175.0 MW solar facility (Garrett County)
    Order No. 90038: January 11, 2022
  • Case No. 9662–Costen Solar, Inc.
    10.625 MW solar facility (Somerset County)
    Order No. 90013: December 21, 2021
  • Case No. 9658–Baltimore Gas and Electric Company
    Five Forks to Windy Edge Transmission Line Reliability Project (Harford County to Baltimore County)
    Order No. 90024: January 4, 2022

2020

  • Case No. 9656–Kumquat & Citron Cleantech, LLC
    7.20 MW solar facility (Wicomico County)
    Application withdrawn March 31, 2022
  • Case No. 9652–PTR Holdco, LLC (Fairview Farm Solar)
    30.0 MW solar facility (Harford County)
    Order No. 89890: July 28, 2021
  • Case No. 9643–Point Reyes Energy Partners, LLC (Jade Meadow Solar)
    19.84 MW solar facility (Allegany County)
    Order No. 89811: May 10, 2021
  • Case No. 9642–Baltimore Gas and Electric Company
    Bush River Crossing Transmission Line Project (Harford County)
    Order No. 89833: June 8, 2021
  • Case No. 9636–Baltimore Gas and Electric Company
    The Five Forks to Maryland/Pennsylvania Border Transmission Line Reliability Project (Harford County)
    Order No. 89686: January 11, 2021
  • Case No. 9635–New Market Solar, LLC
    50 MW solar facility (Dorchester County)
    Order No. 90199: April 27, 2022

2019

  • Case No. 9620–Lightsource Renewable Energy Development, LLC
    20 MW solar facility (St. Mary’s County)
    Application withdrawn July 8, 2021
  • Case No. 9608–Spectrum Solar, LLC
    5.6 MW solar facility (Prince George’s County)
    Order No. 89520: March 2, 2020
  • Case No. 9330–Mattawoman Energy, LLC modifications to existing CPCN
    859 MW facility (Prince George’s County)
    CPCN cancelled: February 5, 2021

2018

  • Case No. 9600–Baltimore Gas and Electric Company
    Key Crossing Reliability Initiative Transmission Line Project (Baltimore County and Anne Arundel County)
    Order No. 89532: March 14, 2020
  • Case No. 9499–Morgnec Road Solar, LLC
    45 MW solar facility (Kent County)
    Order No. 90200: April 27, 2022
  • Case No. 9496–Bluegrass Solar, LLC
    80 MW solar facility (Queen Anne’s County)
    Order No. 89326: October 29, 2019
  • Case No. 9495–Kieffer Funk, LLC
    11.8 MW solar facility (Washington County)
    Order No. 89347: November 14, 2019
  • Case No. 9483–Citizens UB Solar, Inc.
    8.172 MW solar facility (Carroll County)
    Order No. 89548: April 27, 2020
  • Case No. 9482–CP Crane LLC, modifications to existing CPCN (Baltimore County)
    Order No. 89211: July 24, 2019
  • Case No. 9477–Cherrywood Solar I, LLC
    202 MW solar facility (Caroline County)
    Order No. 89096: April 16, 2019

2017

  • Case No. 9471–Transource Maryland, LLC
    Construction of two 230 kV transmission lines (Harford County/ Washington County)
    Order No. 89571: June 30, 2020
  • Case No. 9470–Potomac Edison Company
    Modification of the Ringgold-Catoctin 138 kV Transmission Line (Frederick County/Washington County)
    Order No. 89035: February 15, 2019
  • Case No. 9469–Energy Ventures IPP, LLC
    10 MW solar facility (Prince George’s County)
    Application withdrawn July 2, 2020
  • Case No. 9466–TPE Maryland Solar Land Holdings, LLC
    2.25 MW solar facility (Prince George’s County)
    Application withdrawn March 5, 2018
  • Case No. 9465–TPE Maryland Solar Land Holdings, LLC
    2.425 MW solar facility (Prince George’s County)
    Application withdrawn March 5, 2018
  • Case No. 9464–MD Solar 1, LLC
    32.5 MW solar facility (Charles County)
    Order No. 88841: Sept 21, 2018
  • Case No. 9463–MD Solar 2, LLC
    27.5 MW solar facility (Charles County)
    Order No. 88842: Sept 21, 2018
  • Case No. 9457–Richfield Solar Energy, LLC
    50 MW solar facility (Dorchester County)
    Order No. 89069: March 19, 2019
  • Case No. 9318–Dominion Energy Cove Point LNG, LP (modifications to existing CPCN)
    Order No. 88565: February 6, 2018
  • Case No. 9454–Brick Kiln Road Solar, LLC
    5.4 MW solar facility (Wicomico County)
    Order No. 88562: February 6, 2018
  • Case No. 9451–Chesapeake Solar, LLC
    9.0 MW solar facility (Cecil County)
    Order No. 88634: April 6, 2018
  • Case No. 9450–Casper Solar Center, LLC
    36.7 MW solar facility (Queen Anne’s County)
    Application withdrawn June 14, 2019
  • Case No. 9446–Sol Phoenix Solar, LLC
    2.5 MW solar facility (Prince George’s County)
    Order No. 88462: November 9, 2017
  • Case No. 9439–Biggs Ford Solar Center, LLC
    15 MW solar facility (Frederick County)
    Order No. 89668: November 24, 2020

2016

  • Case No. 9438–Morgnec Road Solar, LLC
    57.04 MW solar facility (Kent County)
    Application withdrawn October 6, 2017
  • Case No. 9437—CPV Maryland, LLC (cpvstcharles.com)
    Modifications to St. Charles Generating Station (Charles County)
    Order No. 88609: March 16, 2018
  • Case No. 9436—Jones Farm Lane Solar, LLC
    56.7 MW solar facility (Queen Anne’s County)
    Order No. 88646: April 17, 2018
  • Case No. 9434—Egypt Road Solar, LLC
    45.9 MW solar facility (Cambridge/Dorchester County)
    Order No. 88659: April 27, 2018
  • Case No. 9429—LeGore Bridge Solar Center, LLC
    20.0 MW solar facility (Frederick County)
    Order No. 88613: March 23, 2018
  • Case No. 9426–Mason Dixon Solar Center, LLC
    18.4 MW solar facility (Washington County)
    Order No. 88166: April 28, 2017
  • Case No. 9413–Dan’s Mountain Wind Force, LLC
    59.5 MW wind facility (Allegany County)
    Order No. 88260: June 16, 2017

2015

  • Case No. 9412–Todd Solar, LLC
    20 MW solar facility (Dorchester County)
    Order No. 87690: July 28, 2016
  • Case No. 9411–Mills Branch Solar, LLC
    60 MW solar facility (Kent County)
    Order No. 88021: February 10, 2017
  • Case No. 9409–Gateway Solar, LLC
    12 MW solar facility (Worcester County)
    Order No. 87941: December 15, 2016
  • Case No. 9408–Perennial Solar, LLC
    8.0 MW solar facility (Washington County)
    Order No. 89938: September 17, 2021
  • Case No. 9407–Massey Solar, LLC
    5.0 MW solar facility (Kent County)
    Order No. 88963: December 31, 2018
  • Case No. 9405–Longview Solar, LLC
    15 MW solar facility (Worcester County)
    Order No. 87556: May 2, 2016
  • Case No. 9403–Longview Solar, LLC
    20 MW solar facility (Worcester County)
    Order No. 87539: May 10, 2016
  • Case No. 9402—Big Spring Solar, LLC
    3.5 MW solar facility (Washington County)
    Order No. 88453: October 31, 2017
  • Case No. 9400–Dan’s Mountain Solar, LLC
    18.36 MW solar facility (Allegany County)
    Order No. 87659: July 11, 2016
  • Case No. 9399–OneEnergy Baker Point Solar, LLC
    9.0 MW solar facility (Frederick County)
    Order No. 87652: July 6, 2016
  • Case No. 9395–Pinesburg Solar, LLC
    8.0 MW solar facility (Washington County)
    Order No. 88053: March 3, 2017
  • Case No. 9392–OneEnergy Ibis Solar, LLC
    6.0 MW solar facility (Somerset County)
    Order No. 87835: October 21, 2016
  • Case No. 9387–OneEnergy Blue Star Solar, LLC
    6.0 MW solar facility (Kent County)
    Letter Order Rescinding CPCN: October 17, 2018
  • Case No. 9383–OneEnergy Sunfish Solar, LLC
    6.0 MW solar facility (Queen Anne’s County)
    Order No. 87380: January 22, 2016
  • Case No. 9380–Great Bay Solar I, LLC
    150 MW solar facility (Somerset County)
    Order No. 87321: December 30, 2015
  • Case No. 9375–OneEnergy Wye Mills Solar, LLC
    10 MW solar facility (Queen Anne’s County)
    Order No. 87061: June 30, 2015

2014

  • Case No. 9370–OneEnergy Dorchester, LLC
    15.5 MW solar facility (Dorchester County)
    Order No. 87012: June 9, 2015
  • Case No. 9367–Delmarva Power & Light Company
    Rebuild of an existing 138 kV overhead transmission line (Queen Anne’s County/Caroline County)
    Order No. 87156: September 10, 2015
  • Case No. 9366–LS-Egret, LLC
    15 MW solar facility (Wicomico County)
    Order No. 87004: May 28, 2015
  • Case No. 9365–Constellation Solar MC, LLC
    20 MW solar facility (Harford County)
    Order No. 86949: April 16, 2015
  • Case No. 9351–Rockfish Solar LLC
    10 MW solar facility (Charles County)
    Order No. 86607: September 16, 2014
  • Case No. 9348–OneEnergy Cambridge Solar, LLC
    3.3 MW solar facility (Dorchester County)
    Order No. 86593: September 5, 2014
  • Case No. 9341–Panda-Brandywine L.P. and KMC Thermo, LLC
    Modifications to Panda-Brandywine Power Plant (Prince George’s County)
    Order No. 86457: July 10, 2014
  • Case No. 9338–H.A. Wagner LLC
    Modifications to the Herbert A. Wagner Generating Station (Anne Arundel County)
    Order No. 86585: September 3, 2014

2013

  • Case No. 9330–Mattawoman Energy, LLC
    859 MW generating facility (Prince George’s County)
    CPCN Cancelled: February 5, 2021
  • Case No. 9329–Potomac Electric Power Company
    Rebuild of an existing double circuit 230kV overhead tower line (Prince George’s County)
    Order No. 86333: May 13, 2014
  • Case No. 9327–Old Dominion Electric Cooperative, Inc.
    1,000 MW generating facility (Cecil County)
    Order No. 86290: April 8, 2014
  • Case No. 9323–Baltimore Gas and Electric Company
    Northeast Transmission System Improvement Project (Harford County/Baltimore County)
    Order No. 86086: December 30, 2013
  • Case No. 9321–Delmarva Power & Light Company
    Rebuild of an existing 138kV overheard transmission line (Cecil County)
    Order No. 86342: May 19, 2014
  • Case No. 9320–Constellation Power Source Generation, Inc.
    Modification of the Riverside Generating Station (Baltimore County)
    Order No. 85899: October 16, 2013
  • Case No. 9318–Dominion Cove Point LNG, LP
    130 MW generating station (Calvert County)
    Order No. 86372: May 30, 2014
  • Case No. 9314–Church Hill Solar Farm, LLC
    6.0 MW solar facility (Queen Anne’s County)
    Order No. 85683: June 24, 2013

2012

  • Case No. 9312–Delmarva Power and Light Company
    Construction of a new 138kV overhead transmission line (Queen Anne’s County)
    Order No. 85959: November 1, 2013
  • Case No. 9309–Potomac Edison Company
    Rebuild of Maryland segment of Mt. Storm-Doubs 500kV transmission line (Frederick County)
    Order No. 85706: July 8, 2013
  • Case No. 9297–Keys Energy Center, LLC
    735 MW generating facility (Prince George’s County)
    Order No. 86692: October 31, 2014

2011

  • Case No. 9282–Baltimore Gas and Electric Company
    Northwest to Deer Park 115kV transmission line extension project (Baltimore County)
    Order No. 84823: April 17, 2012
  • Case No. 9280–CPV Maryland, LLC
    Modification to St. Charles Project (Charles County)
    Order No. 85144: October 10, 2012
  • Case No. 9274–Baltimore Gas and Electric Company
    Perryman to Harford Transmission Line Relocation Project (Harford County)
    Order No. 84584: January 4, 2012
  • Case No. 9272–Maryland Solar LLC
    20 MW solar facility (Washington County)
    Order No. 84377: October 11, 2011
  • Case No. 9268–Big Savage, LLC
    Construction of a 138 kV generator lead line (Allegany County)
    Order No. 84369: October 3, 2011
  • Case No. 9264–Delmarva Power & Light Company
    Construction of 138 kV overhead transmission line (Worcester County)
    Order No. 84461: November 4, 2011
  • Case No. 9251–Baltimore Gas and Electric Company
    Rebuild of Bagley to Graceton 230 kV transmission line (Harford County)
    Application withdrawn: April 5, 2013